Question: An assembly-line worker at Joseph Milners Fabrication Shop inserts Part A into Part B. A time study was conducted and produced the following results in

An assembly-line worker at Joseph Milner’s Fabrication Shop inserts Part A into Part B. A time study was conducted and produced the following results in seconds: 8.4, 8.6, 8.3, 8.5, 8.7, 8.5. What is the average cycle time?

Step by Step Solution

3.40 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Avg observe... View full answer