Question: Complete the available-to-promise table below. Period 3 On-hand = 30 Forecast 100 50 100 50 100 50 Customer 75 50 116 73 45 23 orders

Period 3 On-hand = 30 Forecast 100 50 100 50 100 50 Customer 75 50 116 73 45 23 orders Master 50 100 50 100 100 50 production schedule Available-to- promise 2.
Step by Step Solution
3.45 Rating (158 Votes )
There are 3 Steps involved in it
On hand 30 Period Forecast CO M... View full answer