Question: Complete the master production schedule based on the following information: Additional Information: On-hand inventory: 160 Schedule production whenever projected on-hand inventory drops below 30 MPS
Complete the master production schedule based on the following information:

Additional Information:
On-hand inventory: 160
Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300
4 Week Forecast 120 100 130 110 140 140 170 180 Customer Orders Projected On-Hand Inventory MPS Available-to-Promise (ATP) 100 5 75 50 32 110 11
Step by Step Solution
3.26 Rating (161 Votes )
There are 3 Steps involved in it
Week 1 2 3 4 5 6 7 8 Forecast 120 100 130 11... View full answer