Question: Complete the master production schedule based on the following information: Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS

Additional Information:
On-hand inventory: 600
Schedule production whenever projected on-hand inventory drops below 30
MPS lot size: 300
Production lead time or lead time for MPS releases: 1 week
Week 1 Forecast 320 100 110 40 240 290 60 410 30 Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available-to-Promise (ATP) 60 50 80 20 60 60 8
Step by Step Solution
3.33 Rating (168 Votes )
There are 3 Steps involved in it
Week 1 2 3 4 5 6 7 8 9 Forecast 320 100 30 110 40 ... View full answer