Complete the master production schedule based on the following information: Additional Information: On-hand inventory: 600 Schedule production

Question:

Complete the master production schedule based on the following information:

Week 1 Forecast 320 100 110 40 240 290 60 410 30 Customer Orders Projected On-Hand Inventory MPS Released MPS Due Availa


Additional Information:

On-hand inventory: 600

Schedule production whenever projected on-hand inventory drops below 30

MPS lot size: 300

Production lead time or lead time for MPS releases: 1 week

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Managing Global Supply Chains

ISBN: 978-1506302935

1st edition

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

Question Posted: