Question: Component K has the following weekly demand requirements: The ordering cost for this item is $100/order and holding cost is $1/unit/week (in U.S. dollars). To
Component K has the following weekly demand requirements:
![]()
The ordering cost for this item is $100/order and holding cost is $1/unit/week (in U.S. dollars). To develop a material requirements plan for this component, which of the following lot-sizing techniques will yield the lowest total cost?
1. EOQ.
2. 2-week fixed-period ordering.
3. Lot-for-lot.
4. Part-period balancing (PPB).
Week 8. 4 6. 75 90 40 85 Demand 60 60 130 65 100 30
Step by Step Solution
3.38 Rating (173 Votes )
There are 3 Steps involved in it
1 EOQ Product X Low level code 0 Lead time 1 week WEEK 1 2 3 4 5 6 7 8 9 Gross requirements 60 90 60 ... View full answer