Question: Compute the total cost for each aggregate plan using these unit costs: Regular output $ 40 Overtime $ 50 Subcontract $ 60 Average Balance Inventory
Compute the total cost for each aggregate plan using these unit costs:
Regular output $ 40
Overtime $ 50
Subcontract $ 60
Average Balance Inventory $ 10
a.
-1.png)
b.

c. (Refer to part b) After complaints from some workers about working overtime every month during the first half of the year, the manager is now considering adding some temporary workers for the second half of the year, which would increase regular output to a steady 350 units a month, not using any overtime, and using subcontracting to make up needed output. Determine the total cost of that plan.
Step by Step Solution
There are 3 Steps involved in it
Given Regularcost per unit 40 Overtime cost per unit 50 Subcontract cost per unit 10 Carrying cost per unit per month 10 and is assessed on averageinventory a We have the following aggregateplan Calcu... View full answer
Get step-by-step solutions from verified subject matter experts