Question: Consider a four-step serial process with processing times given in the following list. There is one machine at each step of the process, and this
Consider a four-step serial process with processing times given in the following list. There is one machine at each step of the process, and this is a machine-paced process.
- Step 1: 25 minutes per unit
- Step 2: 15 minutes per unit
- Step 3: 30 minutes per unit
- Step 4: 20 minutes per unit
Assuming that the process starts out empty, how long will it take (in hours) to complete a batch of 105 units?
Step by Step Solution
3.41 Rating (170 Votes )
There are 3 Steps involved in it
54 hours Step 3 is the bottleneck step of the process so the mach... View full answer