Consider the AON graph of a project shown in Figure 19.17. The activity times are 3, 4,
Question:
Consider the AON graph of a project shown in Figure 19.17.
The activity times are 3, 4, 2, 5, 7, 2, 2, and 3 days for activities A1 through A8, respectively. What is the earliest completion time of the project?