Question: Consider the project network diagram shown below. Using this diagram and the activity duration times listed below, calculate the ES,EF,LF times for all activities. In

Consider the project network diagram shown below. Using this diagram and the activity duration times listed below, calculate the ES,EF,LF times for all activities. In addition, Identify the critical path by calculating Slacks associated with each activities. How long will the project take?
A

Activity....................................Duration (days)
A..............................................................4
B.............................................................11
C...............................................................5
D...............................................................3
E................................................................2
F................................................................1
G................................................................4
H................................................................2
I..................................................................3
J.................................................................4

A

Step by Step Solution

3.45 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Critical Path ABGJ Project duration 23 days Draw the table listing ES LS EF LE and ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-F-D-F(808).docx

120 KBs Word File

Students Have Also Explored These Related Corporate Finance Questions!