Question: Consider the project network diagram shown below. Using this diagram and the activity duration times listed below, calculate the ES,EF,LF times for all activities. In
.png)
Activity....................................Duration (days)
A..............................................................4
B.............................................................11
C...............................................................5
D...............................................................3
E................................................................2
F................................................................1
G................................................................4
H................................................................2
I..................................................................3
J.................................................................4
A
Step by Step Solution
3.45 Rating (164 Votes )
There are 3 Steps involved in it
Critical Path ABGJ Project duration 23 days Draw the table listing ES LS EF LE and ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1019-B-C-F-D-F(808).docx
120 KBs Word File