Question: Consider the data given in the following table. The fixed cost is $900 per week. Perform a time-cost tradeoff analysis. What is the minimum cost

Consider the data given in the following table. The fixed cost is $900 per week. Perform a time-cost tradeoff analysis. What is the minimum cost to complete the project and what is the corresponding time?

Immediate Normal Time Crash Time Normal Crash Activity Predecessor (s) (Weeks) (Weeks)

Immediate Normal Time Crash Time Normal Crash Activity Predecessor (s) (Weeks) (Weeks) Cost ($) Cost ($) A None 9 6 13,000 15,550 B None 5 4 7000 7900 C None 7 5 15,000 15,800 D A 12 8 12,000 14,800 E B 8 5 9000 10,500 LL F B 6 4 5000 6200 G C 11 9 13,000 14,000 H D, E 5 4 8000 9000 I F, G, H 4 3 2500 3500 J 10 8 12,000 15,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!