Question: Consider the data given in the following table. The fixed cost is $900 per week. Perform a time-cost tradeoff analysis. What is the minimum cost
Consider the data given in the following table. The fixed cost is $900 per week. Perform a time-cost tradeoff analysis. What is the minimum cost to complete the project and what is the corresponding time?

Immediate Normal Time Crash Time Normal Crash Activity Predecessor (s) (Weeks) (Weeks) Cost ($) Cost ($) A None 9 6 13,000 15,550 B None 5 4 7000 7900 C None 7 5 15,000 15,800 D A 12 8 12,000 14,800 E B 8 5 9000 10,500 LL F B 6 4 5000 6200 G C 11 9 13,000 14,000 H D, E 5 4 8000 9000 I F, G, H 4 3 2500 3500 J 10 8 12,000 15,000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts