Question: Consider the following data for a project to install a new server at the Northland Pines High School. a. Draw the network diagram. b. Calculate
Consider the following data for a project to install a new server at the Northland Pines High School.
a. Draw the network diagram.
b. Calculate the critical path for this project.
c. How much slack is in each of the activities G, H, and I?
Activity A B C D E LL G H I J Activity Time (days) 2 4 LO 5 2 1 8 3 5 4 7 Immediate Predecessor(s) A A B B B, C D, E LL LL G, H, I