Question: Consider the following data for a project never before attempted by your company: a. Draw the network diagram for this project. b. Identify the critical
.png)
a. Draw the network diagram for this project.
b. Identify the critical path and estimate the projects duration.
c. Calculate the slack for eachactivity.
Activity Expected Time t (weeks) Immediate Predecessor(s) C. D
Step by Step Solution
3.45 Rating (168 Votes )
There are 3 Steps involved in it
a The AON diagram is b Critical path is BDF Expected duration of the project is 15 weeks ... View full answer