Question: Consider two processes, A and B, with an initial cost of c(1) = 20. Process A has a learning rate of LR = 0.95 and

Consider two processes, A and B, with an initial cost of c(1) = 20. Process A has a learning rate of LR = 0.95 and process B has a learning rate of LR = 0.8. After 20 units: 

a. Process A is cheaper. 

b. Process B is cheaper. 

c. The two processes will have the same cost. 

d. Cannot be determined from the given information.