Question: The following four jobs must be processed in two processes A and B. All jobs must go through process A first then process B. The

The following four jobs must be processed in two processes A and B. All jobs must go through process A first then process B. The process times are given below in minutes.

The following four jobs must be processed in two processes

a. Determine the optimal order in which the job should be sequenced.
b. Schedule the jobs through the two processes and calculate the percent idle time for thisschedule.

Job Process A Time Process B time 4

Step by Step Solution

3.45 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Using Johnsons rule the job which has lowest time on first process is put at ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

68-B-E-M-E (2135).docx

120 KBs Word File

Students Have Also Explored These Related Economics Questions!