Question: The following four jobs must be processed in two processes A and B. All jobs must go through process A first then process B. The
The following four jobs must be processed in two processes A and B. All jobs must go through process A first then process B. The process times are given below in minutes.
.png)
a. Determine the optimal order in which the job should be sequenced.
b. Schedule the jobs through the two processes and calculate the percent idle time for thisschedule.
Job Process A Time Process B time 4
Step by Step Solution
3.45 Rating (164 Votes )
There are 3 Steps involved in it
a Using Johnsons rule the job which has lowest time on first process is put at ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
68-B-E-M-E (2135).docx