Question: For 120 consecutive days, a process engineer has measured the temperature of champagne bottles as they are made ready for serving. Each day, she took

For 120 consecutive days, a process engineer has measured the temperature of champagne bottles as they are made ready for serving. Each day, she took a sample of 8 bottles. The average across all 960 bottles (120 days, 8 bottles per day) was 46 degrees Fahrenheit. The standard deviation across all bottles was 0.8 degree. When constructing an X-bar chart, what would be the upper control limit?

Step by Step Solution

3.43 Rating (169 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

4684853 degrees Fahrenheit To find the upper control limit we firs... View full answer