Question: Given a total task time of 48 minutes, a desired output of 80 units per day and 2-eight hour shifts per day, what is the
Given a total task time of 48 minutes, a desired output of 80 units per day and 2-eight hour shifts per day, what is the takt time in minutes per unit? What is the minimum number of workcenters ? If the assembly line is balanced with six workcenters , what is the efficiency?
Step by Step Solution
★★★★★
3.42 Rating (161 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Takt time 960... View full answer