Question: Given a total task time of 48 minutes, a desired output of 80 units per day and 2-eight hour shifts per day, what is the

Given a total task time of 48 minutes, a desired output of 80 units per day and 2-eight hour shifts per day, what is the takt time in minutes per unit? What is the minimum number of workcenters ? If the assembly line is balanced with six workcenters , what is the efficiency?

Step by Step Solution

3.42 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Takt time 960... View full answer