Question: If the jobs displayed in Table 18.23 are processed using the earliestdue-date rule, what would be the lateness of job B? TABLE 18.23 Processing Times

If the jobs displayed in Table 18.23 are processed using the earliestdue-date rule, what would be the lateness of job B? 

TABLE 18.23 Processing Times and Due Dates for Five Jobs Job A B C D E Processing time (weeks) 2 0.5 1 3 1.5 Due date (weeks) 3 6 4 5 2

TABLE 18.23 Processing Times and Due Dates for Five Jobs Job A B C D E Processing time (weeks) 2 0.5 1 3 1.5 Due date (weeks) 3 6 4 5 2