Question: Job A B C D E Processing time ( Week ) 2 0 . 5 1 3 1 . 5 Due Datre ( Week )

Job A B C D E
Processing time (Week)20.5131.5
Due Datre (Week)36452
3. If the jobs displayed in Table 18.23 are processed using the earliest-due-date rule, what would be the lateness of job B?
Processing order using earliest-due-date rule: E, A, C, D, B
Flow time for job B =8 weeks. The due date for job B =6 weeks. The lateness for job B =86=2 weeks.