Question: Information concerning the product structure , lead times, end quantities on hand for an electric golf cert is shown in the following table. Use this
Information concerning the product structure , lead times, end quantities on hand for an electric golf cert is shown in the following table. Use this information to do each of the following:
a. Construct the product structure tree.
b. Construct the assembly time chart.
c. Develop the material requirements plan that will provide 200 golf carts at the start of week 8, assuming lot-for-lot ordering.
.png)
Step by Step Solution
There are 3 Steps involved in it
a b c Production Schedule for golf carts Week Beg Inv 1 2 3 4 5 6 7 8 Quantity 200 Item Gold Cart LT 1 wk Beg Inv 1 2 3 4 5 6 7 8 Gross requirements 2... View full answer