Question: It takes 80,000 hours to produce the first jet engine at T.R.s aerospace division and the learning factor is 90%. Help production manager Gopal Easwaran

It takes 80,000 hours to produce the first jet engine at T.R.’s aerospace division and the learning factor is 90%. Help production manager Gopal Easwaran determine how long it takes to produce the eighth engine.

Step by Step Solution

3.37 Rating (169 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Time to produce first engine 80000 hours Learning factor 090 From Table E3 Learning curve coefficien... View full answer