Question: Neptune Enterprises manufactures central processing units (CPUs) for a line of personal computers. Currently, the CPUs are manufactured in three existing plants in Raleigh, Akron,

Neptune Enterprises manufactures central processing units (CPUs) for a line of personal computers. Currently, the CPUs are manufactured in three existing plants in Raleigh, Akron, and Cedar Rapids. The company is considering adding a fourth plant in one of two locations: Mobile or Atlanta. Relevant data on shipping costs, capacities, and demand requirements for both the existing plants and destinations, and the proposed plants and destinations are given in the following tables. In which location should the fourth plant be added?

Destinations Existing Plants Capacity 350 Miami Houston Seattle $22 Raleigh Akron $23 $19 $27 250 $29 $27 $22 $24 Cedar


Destinations Proposed Plants Miami Houston Capacity Seattle $31 $31 200 $30 Mobile Atlanta $28 $30 $32 200

Destinations Existing Plants Capacity 350 Miami Houston Seattle $22 Raleigh Akron $23 $19 $27 250 $29 $27 $22 $24 Cedar Rapids 200 $24 310 Damand 290 400 Destinations Proposed Plants Miami Houston Capacity Seattle $31 $31 200 $30 Mobile Atlanta $28 $30 $32 200

Step by Step Solution

3.44 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Destinations Existing Plants Miami Seattle Houston Capacity Raleigh 60 290 0 35... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!