Question: Refer to problem 22. Given the data and the product structure tree provided in that problem, develop a material requirements plan for all the nine
Refer to problem 22. Given the data and the product structure tree provided in that problem, develop a material requirements plan for all the nine items.
Data form problem 22
Refer to the product structure tree and the following data:



C (1) E (1) D (1) B (1) 2) K (2) G (1) 2) F (1) (2 K (1) Week 10 11 12 13 14 15 Gross Requirements for A 90 80 100 50 70 90
Step by Step Solution
3.34 Rating (166 Votes )
There are 3 Steps involved in it
Product Finished Unit A Low level code 0 Lead time 1 weeks Lot size L4L DAY 10 11 12 13 14 15 Gross requirements 90 80 100 50 90 70 Scheduled receipts ... View full answer