Question: Refer to the data in problem 6. If backorders are allowed, determine the total cost of a plan if overtime is limited to 40 units
Data from problem 6
Given the following forecast and cost information, determine the total cost of a plan that uses regular time production output of 600 units per month, overtime is used when needed up to a maximum of 60 units per month, and subcontracting is used if additional units are needed to meet the forecast:
![]()
Regular time cost = $40 per unit
Overtime cost = $60 per unit
Subcontracting cost = $80 per unit
Holding cost = $10 per unit per month
Month 690 Forecast 570 600 630 670 650
Step by Step Solution
3.26 Rating (172 Votes )
There are 3 Steps involved in it
If the SOP must satisfy all demand then this plan yields a cost of 40 x 3600 ... View full answer