Suppose for problem 2, you found a new supplier who could guarantee deliveries, allowing you to change
Question:
Suppose for problem 2, you found a new supplier who could guarantee deliveries, allowing you to change project variance to 9 days.
1. Recalculate the probabilities of finishing the project in 50, 70, and 90 days.