Question: You have a project with an expected completion time of 15 weeks and a project variance of 4 weeks. 1. What is the probability the
You have a project with an expected completion time of 15 weeks and a project variance of 4 weeks.
1. What is the probability the project will be completed in 12 weeks?
2. What is the probability the project will be completed in 15 weeks?
3. What is the probability the project will be completed in 18 weeks?
4. If your investors need 95% probability assurance, what is the due date that yields this 95% likelihood of completion?
Step by Step Solution
3.41 Rating (186 Votes )
There are 3 Steps involved in it
1 Pcompleted within 12 wee... View full answer
Get step-by-step solutions from verified subject matter experts
