You have a project with an expected completion time of 15 weeks and a project variance of

Question:

You have a project with an expected completion time of 15 weeks and a project variance of 4 weeks.
1. What is the probability the project will be completed in 12 weeks?
2. What is the probability the project will be completed in 15 weeks?
3. What is the probability the project will be completed in 18 weeks?
4. If your investors need 95% probability assurance, what is the due date that yields this 95% likelihood of completion?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Managing Global Supply Chains

ISBN: 978-1506302935

1st edition

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

Question Posted: