The following jobs are waiting to be processed at a small machine center: All dates are specified

Question:

The following jobs are waiting to be processed at a small machine center:

All dates are specified as manufacturing planning calendar days.
Assume that all jobs arrived on day 210 (yesterday) in the order shown but are not scheduled to begin until day 211 (today).
a) Sequence the jobs according to LPT.
b) What is the average completion (flow) time?
c) What is the average job lateness?
d) What is the average number of jobs in the system?