Question: Given a network for an HR training project with normal times and crash times (in parentheses), find the cost-duration history. Assume indirect costs for facilities
.png)
Activity 1-2: Obtain room 2-3: Select trainer 3-4: Invite e Time Reduction, Direct Cost per Day $30 first, $50 seconod $80 $25 first, $60 second 2-4: Check budget $30 first, $70 second, $90 third 614) 815) 4. 514) 614)
Step by Step Solution
3.48 Rating (174 Votes )
There are 3 Steps involved in it
The critical path is defined by the events 1234 The normal duration is 17 days and a ... View full answer