Question: What would be the desired completion days, if you needed a 98% confidence level? Which non-critical activities should be monitored closely? Why?

What would be the desired completion days, if you needed a 98% confidence level? Which non-critical activities should be monitored closely? Why?

Step by Step Solution

3.33 Rating (147 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Ztable value for 98 is 206 Then 206 DCT 113... View full answer