Question: Which priority rule for scheduling achieves lower work-in-process inventory? a) First come, first served (FCFS) b) Earliest due date (EDD) c) Shortest processing time (SPT)
Which priority rule for scheduling achieves lower work-in-process inventory?
a) First come, first served (FCFS)
b) Earliest due date (EDD)
c) Shortest processing time (SPT)
d) Slack per remaining operations (S/RO)
Step by Step Solution
3.39 Rating (155 Votes )
There are 3 Steps involved in it
c Shor... View full answer