Question: Williston Technologies wishes to use MRP methodology to develop a plan for the next 9 weeks. Williston Technologies has gathered the following information: a. Using
Williston Technologies wishes to use MRP methodology to develop a plan for the next 9 weeks. Williston Technologies has gathered the following information:
a. Using MRP methodology, how much of parts A, B, C, and D should be ordered, and when should they be ordered?
b. Based on the material requirements plan developed for Williston Technologies, how much of parts A, B, C, and D will remain in inventory at the end of week 9?
c. Williston Technologies has just learned that the order for 200 As appearing in week 4 has been cancelled. How does this change the material requirements plan?
Bill of materials B D Current Inventory Records Part Lead Time (Weeks) Lot Size Inventory Currently on Hand A LFL 100 B 2 50 150 C 2 25 50 D 3 LFL 150 Master Production Schedule Weeks Part 1 2 3 4 5 LO 6 7 8 9 A 50 0 50 200 0 0 100 0 100
Step by Step Solution
3.46 Rating (149 Votes )
There are 3 Steps involved in it
Using MRP methodology how much of parts A B C and D should be ordered and when should they be ordere... View full answer
Get step-by-step solutions from verified subject matter experts