Question: 1. Consider Problem 2, Set 6.Sb. The estimates (a, m, b) are listed below. Determine the probabilities that the different nodes of the project will
1. Consider Problem 2, Set 6.Sb. The estimates
(a, m,
b) are listed below. Determine the probabilities that the different nodes of the project will be realized without delay.
Project
(a) Project (b)
Activity
(a, m,
b) Activity
(a, m,
b) Activity (a,m,
b) Activity
(a, m, b)
1-2 (5,6,8) 3-6 (3,4,5) 1-2 (1,3,4) 3-7 (12,13,14)
1-4 (1,3,4) 4-6 (4,8,10) 1-3 (5,7,8) 4-5 (10,12,15)
1-5 (2,4,5) 4-7 (5,6,8) 1-4 (6,7,9) 4-7 (8,10,12)
2-3 (4,5,6) 5-6 (9,10,15) 1-6 (1,2,3) 5-6 (7,8,11)
2-5 (7,8,10) 5-7 (4,6,8) 2-3 (3,4,5) 5-7 (2,4,8)
2-6 (8,9,13) 6-7 (3,4,5) 2-5 (7,8,9) 6-7 (5,6,7)
3-4 (5,9,19) 3-4 (10,15,20)
Step by Step Solution
3.40 Rating (150 Votes )
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
