Question: Develop the B&B tree for each of the following problems. For convenience, always select x1 as the branching variable at node 0. * (a) Maximize
Develop the B&B tree for each of the following problems. For convenience, always select x1 as the branching variable at node 0.
*
(a) Maximize z = 3x1 + 2x2 subject to 2x1 + 5x2 … 18 4x1 + 2x2 … 18 x1, x2 Ú 0 and integer
(b) Maximize z = 2x1 + 3x2 subject to 7x1 + 5x2 … 36 4x1 + 9x2 … 35 x1, x2 Ú 0 and integer
(c) Maximize z = 2x1 + 2x2 subject to 2x1 + 5x2 … 27 6x1 + 5x2 … 16 x1, x2 Ú 0 and integer
*
(d) Minimize z = 5x1 + 4x2 subject to 3x1 + 2x2 Ú 5 2x1 + 3x2 Ú 7 x1, x2 Ú 0 and integer
(e) Maximize z = 5x1 + 7x2 subject to 2x1 + x2 … 13 5x1 + 9x2 … 41 x1, x2 Ú 0 and integer
Step by Step Solution
There are 3 Steps involved in it