Question: Do Exercise 12-15 for the averagecompletion- time, single-machine scheduling ILP min 0.51x1 + 12 + x2 + 82 s.t. x1 + 12 x2 +
Do Exercise 12-15 for the averagecompletion-
time, single-machine scheduling ILP min 0.51x1 + 12 + x2 + 82 s.t. x1 + 12 … x2 + 7511 - y2 x2 + 8 … x1 + 75y x1, x2 Ú 0 y = 0 or 1 with LP relaxation optimum x = 10, 02, y = 0.08.
[Hint: Consider the sum of the process times in part (a).]
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts