Question: 14. A control chart shows seven data points m a row on one side of the mean. What should the project manager do? A. Perform
14. A control chart shows seven data points m a row on one side of the mean. What should the project manager do?
A. Perform a design of experiments.
B. Adjust the chart to reflect the new mean.
C. Find an assignable cause.
D. Nothing. This is the rule of seven and can be ignored.