Question: 17. You arc working collaboratively with the team to plan a project. You have obtained estimates from team members on the activities for which they

17. You arc working collaboratively with the team to plan a project. You have obtained estimates from team members on the activities for which they each will be responsible. You are currently reaching agreement on the calendar dates for each activity. Which of the foll owing processes are you working on?

A. Sequence Activities B. Develop Schedule C. Defu1e Scope D. Develop Project Charter