18. A proj<•ct manager is in the middle of executing .1 large construction project when he discovers the time needed to complete the pro)f~Ct is longer than thr time availabk What is the best thing to do?
A. Cut product scope.
B. 1\leet with management, and teU them the required date cannot be met.
C. Work overtime.
D. Dc.!tcrmine options for schedule compression, and present management with the recommended option.