Question: 19. You just discovered an error in the implementation plan that will prevent you from meeting a milestone date. Up to this point, your project
19. You just discovered an error in the implementation plan that will prevent you from meeting a milestone date. Up to this point, your project has been running true to its baselines, and you will be delivering a routine status report tomorrow. The milestone in question is not on the critical path, but it is on a nearcritical path. What is the best thing you can do?
A. Develop options to meet the ntilestonl' date.
B. Change the milestone date.
C. Remove any discussion about dates in the project status report.
D. Educ.tic the tc.11n about the need tu meet mile ston e~.