Question: You have just discovered an error in the implementation plan that will prevent you from meeting a milestone date. The BEST thing you can do

You have just discovered an error in the implementation plan that will prevent you from meeting a milestone date. The BEST thing you can do is:

Select one: a. Develop options to meet the milestone date. b. Change the milestone date. c. Remove any discussion about dates in the project status report. d. Educate the team about the need to meet milestones.