Question: 2. A project manager gathered data to perform earned ,alue calculations on his project. He used the results to report to management that the project

2. A project manager gathered data to perform earned ,·alue calculations on his project. He used the results to report to management that the project is under budget and on schedule. After reporting this 111form.1t1on, he disco,·ered the base figures he used in the calculations were incorrect, as they came from an ,1ld copy of the project tile that had not bt!en updated. What should he do now?

A. He should contact inanagc•ment .md tell them to expect some changes in the next reporting period as things .ire s t.irting to look gloomy.

B. He should contact management to m.ikc them aware oithc error, provide the correct information, and explain hmv he made the mistake.

C. He should use the correct figures to calculate the mformation when it is time for the next report and ignore the fact that he reported incorrect information.

D. He should tell management that he received incorrect data from team member~, resulting in an inaccurate report.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!