Question: A project manager gathered data to perform earned value calculations on his project. He used the results to report to management that the project is
A project manager gathered data to perform earned value calculations on his project. He used the results to report to management that the project is under budget and on schedule. After reporting this information, he discovered the base figures he used in the calculations were incorrect, as they came from an old copy of the project file that had not been updated. What should he do now?
A He should contact management and tell them to expect some changes in the next reporting period as things are starting to look gloony
B He should contact management to make them aware of the error, provide the correctinformation, and explain how he made the mistake.
C He should use the correct figures to calculate the information when it is time for the next report and ignore the fact that he reported incoriect information.
D He should tell management that he received incorrect data from team members, resulting in an inaccurate report.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock