Question: 4. A pro1ect has faced mOIJOr difficulties m the quality of its deliverables. Management now states that quality is the most important project constraint. If

4. A pro1ect has faced mOIJOr difficulties m the quality of its deliverables. Management now states that quality is the most important project constraint. If another problem with quality were to occur, what would be the best thmg for the project manager to do?

A. FLx the problem as soon as possible.

B. Allow the schedule to slip by cutting cost.

C. Allow cost to increase by fixing the root cause of the problem.

D. Allow risk to increase by 1.."Ut\ing cost.