Question: 8. Your organization has historically performed projects using a predictive methodology. You'd like to give the agile process a try. You have a low-risk, low-priority
8. Your organization has historically performed projects using a predictive methodology. You'd like to give the agile process a try.
You have a low-risk, low-priority project that is perfect for this experiment. However, the project sponsor of this project is nervous about using a new approach that's never been tried before.
Which of the following actions should you take in this scenario?
A. Make certain you are allocating time to mentoring stakeholders.
B. Ensure that the sponsor is committed to the project and to the methodology.
C. Mentor the sponsor and the stakeholders on the agile process by providing training to educate them on the agile processes.
D. Consider using a hybrid approach to help the sponsor feel a little more at ease, because this will mix some of the processes with which they are familiar with agile processes.
E. All of the above.