Question: A contract change control system should include: A. Vendor contact information, tracking systems, and approval levels necessary for authorizing changes B. Paperwork, tracking systems, dispute
A contract change control system should include:
A. Vendor contact information, tracking systems, and approval levels necessary for authorizing changes B. Paperwork, tracking systems, dispute resolution procedures, and approval levels necessary for authorizing changes C. Information database, dispute resolution procedures, and approval levels necessary for authorizing changes D. Tracking systems, legal ramifications for certain actions, and approval levels necessary for authorizing changes