Question: Please answer all questions 1) A project manager is working on the manage quality phase of a project. He is looking for an alternative means

Please answer all questions

1) A project manager is working on the manage quality phase of a project. He is looking for an alternative means to improve quality and eliminate activities that don't add value. Which of the following will help him do this?

Group of answer choices

a) Continuous process improvement

b) Quality control measurements

c) Quality checklist

d) Team rewards

2) A control chart is used to determine whether or not a process is stable or has predictable performance. When a process is within acceptable limits, the process need not be adjusted. What are the upper and lower control limits usually set as?

Group of answer choices

a) + / - 3 sigma

b) + / - 6 sigma

c) + / - 2 sigma

d) + / - 1 sigma

3) You are fairly new to project management but have been successfully managing a small project, and now management has given you another project to manage, which you are excited about. However, the new project is growing exponentially every day, you have also learned a project manager you work with managed a similar project last year. What should you do?

a) Speak to the other project manager to develop your project plans.

b) Wait to see if the scope of the project continues to grow.

c) Get the project assigned to the PM who managed the similar project.

d) Obtain historical records and get guidance from the project manager.

4) A contract change control system should include which of the following?

Group of answer choices

a) Tracking systems, legal ramifications for certain actions, and approval levels necessary for authorizing changes

b) Information database, dispute resolution procedures, and approval levels necessary for authorizing changes

c) Paperwork, tracking systems, dispute resolution procedures, and approval levels necessary for authorizing changes

d) Vendor contact information, tracking systems, and approval levels necessary for authorizing changes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!