Question: A general contingency is used for a. Risks that are identified at the outset of the project b. Risks that are not identified at the
A general contingency is used for—
a. Risks that are identified at the outset of the project
b. Risks that are not identified at the outset of the project but are known before they occur
c. Risks that cannot be known before they occur because they are external risks
d. Any risks that cannot be known before they occur