Question: A lessons learned session should be held at what point in a project? A. At the project conclusion B. When something goes wrong
A lessons learned session should be held at what point in a project? ❍ A. At the project conclusion ❍ B. When something goes wrong ❍ C. At key milestones ❍ D. When risk events occur