Question: A project manager asked various stakeholders to determine the probability and impact of a number of risks. He then analyzed assumptions. He is about to

A project manager asked various stakeholders to determine the probability and impact of a number of risks. He then analyzed assumptions. He is about to move to the next step of risk management. Based on this information, what has the project manager forgotten to do? A. Evaluate trends in risk analysis. B. Identify triggers. C. Provide a standardized risk rating matrix. D. Create a fallback plan.