Question: A project manager asked various stakeholders to determine the probability and impact of several risks that had been identified. He then analyzed assumptions. He is
A project manager asked various stakeholders to determine the probability and impact of several risks that had been identified. He then analyzed assumptions. He is about to move to the next step of risk management. Based on this information, what has the project manager forgotten to do
Group of answer choices
Create a fallback plan
Provide a standardized risk rating matrix.
Evaluate trends in risk analysis
Identify triggers.