Question: A project manager is determining dependencies that will require a lead or a lag to accurately define the logical relationship. Which of the following correctly
A project manager is determining dependencies that will require a lead or a lag to accurately define the logical relationship. Which of the following correctly describes leads or lags?
A. A lead allows a successor activity to be delayed.
B. A lag directs a delay in the predecessor activity.
C. A lag allows an acceleration of the successor activity.
D. A lead allows an acceleration of the successor activity.