Question: While analyzing the risks in a project, a project manager came up with a Risk Urgency Assessment document. In which process would this be done?
While analyzing the risks in a project, a project manager came up with a Risk Urgency Assessment document. In which process would this be done?
A. Close Risks B. Control Risks C. Perform Qualitative Risk Analysis D. Plan Risk Management